Initial phase of major M8 footbridge repairs completes after two consecutive weekend closures
M8 J21-23 Footbridge Refurbishments programme is a project that will see the refurbishment of all four footbridges over the M8 at this location and will be undertaken in two phases
Amey, on behalf of Transport Scotland, is undertaking essential refurbishments of the Cornwall Street and Kirkwood Street footbridges that span the M8 between Junction 21 (Scotland Street) and Junction 23 (Dumbreck), to the south-west of Glasgow city centre.
The initial phase of the project to maintain these 50-year-old structures has been successfully completed, involving two consecutive weekend closures of 16 lanes of Scotland’s busiest motorway to remove five suspended spans from the bridges for refurbishment off-site.
In total, over two weekends, specialist equipment deployed included the set-up and de-rigging of a 500T crane on the M8 westbound secondary carriageway, a 750T crane on the westbound mainline carriageway, a 650T crane on the eastbound mainline carriageway, and 450T crane on the eastbound secondary carriageway. These cranes removed footbridge spans with weights ranging from 42T to 105T.


The project achieved a 50% reduction in traffic flows, each weekend, and marks excellent collaboration between Amey, Transport Scotland, appointed Contractors Diack and Macaulay (and their Sub-Contractors) and Apex Traffic Management.
Over 136 staff were on-site to maximise the efficiency of the closures, completing cyclic maintenance such as vegetation clearance and renewing road markings, while ensuring the safety of the team. A tight closure timeline was in place and through successful collaborative working, the M8 re-opened to road users two hours ahead of programme during Weekend One and six hours ahead of programme during Weekend Two.
Subsequent Phases
Upon removal of the spans, four weeks of concrete repairs, inspections and on-site testing was undertaken. A further 14 weeks of structural investigation, laboratory testing, and analysis is now underway, which will be followed by off-site refurbishment of the suspended spans. Amey will stand-down the site on Friday 18th October 2024, returning in early Spring 2025 to commence the next phase of the works, which will see the suspended spans repaired, strengthened, and reinstalled.
Signed pedestrian diversions will remain in place during this period.