Insurance hearing will decide the fate of Glasgow School of Art Mackintosh Building rebuild

An insurance arbitration hearing next month will be the most significant moment for the restoration of the Charles Rennie Mackintosh building since the devastating fire in 2018.

The future direction of restoration plans for The Glasgow School of Art’s world-renowned Mackintosh Building will depend on the outcome of an insurance arbitration hearing. The process will decide where the responsibility lies for the funding of a rebuild projected to cost in excess of £100 million.

The A-listed landmark, one of the most significant structures in Scotland was seriously wounded by a fire in 2014. Near the conclusion of a delicate restoration project that followed, the building was gutted by a devastating fire in 2018 that also led to the partial demolition of the neighbouring ABC building on Sauchiehall Street.

A Glasgow School of Art spokesperson has confirmed to Architects’ Journal that the outcome of the arbitration hearing will decide the business case for moving forward. The hearing will take place next month with a report to follow that will clarify responsibility for the financing of the rebuild.

In July 2024, the art school appointed a dual set of architects to rewrite the masterplan for restoration. Reiach and Hall were appointed with Purcell to “robustly test” the Art School’s plans. That announcement also signalled a pause in the process of restoring the fire-ravaged building. The announcement stated that the review would produce a new plan for the building by 2025.

Delphine Dallison views saved tapestries as members of staff and specialist removers continue the retrieval of student art work from the Glasgow School of Art on May 28, 2014placeholder image
Delphine Dallison views saved tapestries as members of staff and specialist removers continue the retrieval of student art work from the Glasgow School of Art on May 28, 2014 | Getty Images

In May 2024, the school conceded that work to restore Charles Rennie Mackintosh’s masterpiece will not be complete in the next decade. The stark admission came as work that had been undertaken since 2018 ground to a halt. Legal wrangles took precedence and an arbitration process with their insurers began.

The school submitted an insurance claim after the 2018 fire. A Scottish Fire and Rescue Service report into the second blaze determined that the cause would never be known conclusively.

“Following publication of the report insurers requested further information which the GSA provided to enable them to confirm policy cover,” a spokesman said.

“In the absence of this confirmation the GSA has chosen to initiate arbitration. The arbitration process is subject to a confidentiality provision which means we are not able to disclose any further details”.

Should an insurance claim not be approved, the art school has stated it would request assistance from the government to secure funding to continue the process.

Work to date has totalled around £18 million, funded by interim payments from the insurers.

Last month, concerns were raised around plans to build a more than 350 bed student accommodation block in place of the ABC Building. The Glasgow School of Art said the plan could cause "permanent degradation" to the neighbouring Mackintosh Building. Two hearings took place to decide the future of the site, with a Scottish government appointed reporter hearing evidence from both developers Vita Group and the Glasgow School of Art.

Evidence was also heard from Glasgow City Council, that approved the plans in June, and Historic Environment Scotland, that previously objected to the plans. A report from the Scottish Government is expected before May this year.

Follow us